risk question
Submitted by pmasp1 on Fri, 12/02/2011 - 02:03
Being the project manager in a high-risk electronics project with a lot of new
technologies, you developed a risk management plan and identified risks which
you documented in a risk register. Then, the risks were analyzed and response
planned.
It is getting obvious during risk monitoring and control meetings that the
documents you created are not very helpful. What have you probably done
wrong?
o You failed to use an RBS.
o You did the first processes alone.
o You did not identify Triggers.
o You did not calculate EMVs.
Forums:
admin
Sat, 12/03/2011 - 18:09
Permalink
Since the question says that
Since the question says that documented risks are not very helpful, I would go with option C.
However if the question said that documented risks are not the real risks, then I would go with option A.