Question related to Close Process - PMP
Submitted by hemald on Thu, 08/20/2015 - 04:21
Which one of the following is the last step of project closing?
1) Archive Project Documents
2) Measure customer satisfaction at the end of the project
3) Client appreciates your product
4) Lessons learnt are documented
Please explain which answer is correct and why?
Thanks
Hemald
Forums:
vishwanathkanchipmp
Thu, 08/20/2015 - 06:02
Permalink
1
1
hemald
Thu, 08/20/2015 - 13:46
Permalink
Thanks - But test site mentions 2
Thanks for this Information.
But the test site mentions answer as 2.
Therefore, I was confused.
admin
Mon, 08/24/2015 - 05:01
Permalink
Usually you measure customer
Usually you measure customer satisfaction first and then archive the project docuemnts.