Question related to Close Process - PMP

Which one of the following is the last step of project closing?
 
1) Archive Project Documents
2) Measure customer satisfaction at the end of the project
3) Client appreciates your product
4) Lessons learnt are documented
 
Please explain which answer is correct and why?
 
Thanks
Hemald
vishwanathkanchipmp's picture

1

Thanks for this Information.

But the test site mentions answer as 2.

Therefore, I was confused.

 

admin's picture

Usually you measure customer satisfaction first and then archive the project docuemnts.