plan risk response..

hi ..

a- should I plan risk response for the items in the watchlist??

b- does (risk owner) means (risk response owner)?

 

admin's picture

a - No.

B - No, Risk owner can be the Sponsor , program manager etc. but risk response owner is the person taking action item. If the risk is lack of resources, the risk owner can be the PM, and risk response owner can be resource manager of the project.