Free PMP Exam Sample Question

The following PMP® exam sample question is taken from the Free PMP Exam Simulator:

------------------------------

Which of the following Enterprise Environmental Factors does not influence the Estimate Activity Durations process?

A.) Duration Estimating Databases
B.) Project Management Information Systems
C.) Productivity Metrics
D.) Published Commercial Information

------------------------------
Hint: All of the given choices are valid Enterprise Environmental Factors but which one of them is not relevant to the Estimate Activity Durations process?
------------------------------

All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

Please click here for the correct answer and explanation.