Finish-to-start question
Submitted by jiawang46 on Wed, 11/29/2017 - 17:10
Hi,
I have a question regarding the "finish-to-start" relationship:
"A schedule activity may begin 10 days before the predecessor activity finishes."
Why this is an example of "finish-to-start" relationship? The successor actually starts 10 days before the predecessor finishes, not that the successor starts after the predecessor finishes. So I am very confused here.
Thanks for sharing your feedback!
Forums:
RyanGrant
Fri, 07/27/2018 - 05:33
Permalink
Hi Jia
When predecessor finishes or completes then only successor activity will start.
Precedence Diagramming Method incorporates four kinds of dependencies or logical predecessor-successor relationships:
Start-to-Start
Start-to-Finish
Finish-to-Start
Finish-to-Finish
You are in confusion so, I am Telling only about Finish-to-start relationship.
Finish-to-Start: Until the predecessor activity is complete, the successor activity cannot start.
Invensis
Sat, 07/28/2018 - 05:34
Permalink
"finish-to-start" relationship:
Successor activity is allowed to start early, and it is pertinent to Finish-to-Start type support, which is a most basic connection between activities. A Lead enables successor activity to begin soon.And also you can refer the follow link which showcase the relationship of the finish to start relationship with diagramatically.
https://www.invensislearning.com/resources/pmp/the-purpose-of-sequence-a...