Cost management questions
Submitted by NISHA on Sat, 06/27/2015 - 19:16
Hi Guys,
I am getting confused with some of these answers,Please help me answering these questions to clear my concept:-(
- Reserve Analysis a technique NOT used in:
- Estimate Costs
- Determine Budget
- Control Costs
- Estimate Activity Duration
- _______ is not part of the Earned Value calculations.
- Known Unknowns
- Unknown Unknowns
- Project Budget
- Amount of work completed
- What is the BEST way to make an accurate forecasting of ETC?
- Manual Forecasting of cost of remaining work.
- BAC – EV
- (BAC – EV)/CPI
- EAC - AC
- Which of the following is not done as part of Performance Measurements?
- Calculating Planned Value
- Calculating Earned Value
- Calculating ETC
- Calculating Cost Variance
- A particular project in the domain of civil construction requires that every on-site worker be insured. Which of the following inputs BEST conveys this requirement to the Cost Estimation process so that the insurance cost is estimated and subsequently budgeted?
- Enterprise Environmental Factor
- Organizational Process Assets
- Project Scope Statement
- Project Management Plan
oorvashe
Sun, 06/28/2015 - 09:38
Permalink
what is the source of the questions?
Hi Nisha,
Good day. what is the source of the questions. I passed PMP on 26th June 2015 and only pmstudy and pm exam simulator are similar to real exam. Real exam has excellent questions and very tricky. Have you tried scordo questions. there are 18 chapters which has 50 questions each.
I just practised 12 chapters from scordo, pm study questions and pm exam simulator(paid one which had 1800 questions and is close to real exam. the exam is available knowledge area wise, process groupwise).
NISHA
Tue, 06/30/2015 - 06:50
Permalink
Hi..
Source of this question is below.
http://preparepm.com/pmp/cost.html
admin
Wed, 07/01/2015 - 03:02
Permalink
The answers are given on same
The answers are given on same page, which question / answer you are confused with and why ?
NISHA
Wed, 07/01/2015 - 05:52
Permalink
Answers
Hi..
I am confused due to these points.
1-Reserve analysis is the tool and technique in all these processes.
2-Uknown-Uknown is not the part of Earned value calculation
3Manual Forecasting of cost of remaining work or it is intended to say re-estimating.
4-Calculating Earned Value is not part of performance measurement?
5-If it is requires that everyone on site should be insured. Does not this come as Enterprise Environmental Factor?
Nisha
oorvashe
Wed, 07/01/2015 - 11:16
Permalink
here it is
1. Reserve Analysis is to analyse the contingency reserve as to how much is utilised and how much more is required for future.
2. reserves used for unknown-unknown is called management reserve. This is part of budget and not included in cost baseline. while contingency reserve is part of both budget and cost baseline.
3.Manual forecasting(bottom up estimating) is done when all the previous cost is incorrect.
4.Earn value management is commonly used method of performance measurement.
5. "requires that every on-site worker be insured" This is a regulation or rule which is part of EEF.
NISHA
Wed, 07/01/2015 - 11:26
Permalink
Thnak you oorvashe..
Thank you oorvashe..for the reply..Actually i am confused with the question itself.
My observation-Reserve analysis is the T & T in all these procsses.so how can we choose on e where it is not.
My observation-This i can understand i beleive that if it is Unknown Unknowns,We cant forecaste anything.
My observation-Thank you for this I didnot know that Manual estimating is bottom up estimating.
My observation-If it is mandatory that all the on-site staff should be insuredd shold be EEF but the answer given is C(Project statement).
Please suggest.
Source-http://preparepm.com/pmp/cost.html
Thankk you
Nisha
oorvashe
Wed, 07/01/2015 - 12:10
Permalink
Move to different mock tests
As i said in my early post, dont waste time in these questions. I took PMP last friday and there are no questions like this...
NOT means...three answers are related and one is not.
Try PMStudy(free and sample version available) or pm exam simulator(170 questions free for 3 days and if you pay you get 1800 questions) and try to score 80% you will defnitely pass the exam. You can also try Scordo tests (1000 questions) free if you are a PMI member.
NISHA
Wed, 07/01/2015 - 14:25
Permalink
Thanks appreciate it..
Thank you so much oorvashe..I am sure you are right..
Will follow the same..
It has been a great help..
Thank you so much..
Nisha..
pmalik
Fri, 09/22/2017 - 09:07
Permalink
EVM Questions
These are all EVM Questions. For help in answering these questions you should read the following articles:
Earned Value Management Formulas
Estimate to Complete – 3 ETC Formulas For PMP Exam
Earned Value Management System Explained in Easy Language
To Complete Performance Index – TCPI Formula & Calculations Explained
Estimate At Completion – 5 EAC Formulas for PMP Exam
Basics of Earned Value Analysis
Sanjay Kumar
Sat, 05/19/2018 - 06:45
Permalink
Daily Question Post
A Facebook page will help you to increase your knowledge about PMP. And A free Cost Management Test at Testudaan is available.