Cost baseline is usually represented using which curve or line?

Cost baseline is usually represented using which curve or line?

  1. Slanted line
  2. Z curve
  3. S-curve
  4. PQ curvec.

Answer : 'C' - S curve

The cost is low in the beginning and end, and high during the middle of the project.