project scope planning process
Submitted by Anonymous (not verified) on Wed, 11/28/2007 - 23:22
Forums:
During the project scope planning process, the work breakdown structure should be developed to:
a. The sub-project level
b. The level determined by the project office
c. A Level allowing for adequate estimates
d. The cost center level
The question talks about scope planning process (not define or create WBS). Wouldn't it be choice B in this case?