Q4 Question : Matrix organizations exhibit features of both projectized and functional organizations. In a Weak Matrix organization, the role of a project manager is that of a:
1. coordinator and expediter
2. project manager with considerable authority
3. support person
4. functional manager
4. Correct Choice: 1
Justification: Weak matrix organizations maintain many of the features of a functional organization and the project manager role is more that of a coordinator or expediter than that of a manager.