Q. You are the project manager at a leading manufacturer of consumer electronics, personal computers and peripherals. You have been assigned a project to drive growth and profit by integrating an online CRM (customer relationship management) solution. The project is nearing completion. Which of the following is an output of close project or phase process?

A.Organizational process asset updates
B.Project management plan updates
C.Accepted deliverables
D.Work performance reports

Ans?