PMP Quiz - Question of the day 08-02-2018

Sanjay Kumar's picture

Q. Monika have been one of the oldest and most experienced project manager, the company "Aion Airways" had. Recently the company was facing few challenges on managing the lead to revenue process. There have been huge revenue leakages due to issues in the process. The CIO authorized Monika to look into the process and come up with a plan to decrease revenue losses by 10% in next six months. Monika categorized the stakeholders in some categories. Some stakeholders are very negative about the outcome of the project and speaks the same. Which category these stakeholders fall under?
A. Resistant
B. Neutral
C. Supportive
D. Leading
What should be correct answer?