Q. You are conducting a status meeting and monitoring your risk register when you discover a risk that remains even after you implement all of your response strategies. What kind of risk is this and what should you do about it?

A. It’s a secondary risk; you don’t need to worry about it

B. It’s a residual risk; you need to plan a response strategy for it

C. It’s a residual risk; you don’t need to plan a response strategy for it because you’ve already implemented all of the risk responses you can plan for

D. It’s a contingency reserve. You should only use it if the first risk occurs

Answer should be

Source=Click Here