Formulas for PMP
Updated: 19th Sept.
If you think a formula is missing here but required in PMP exam. Post a comment and we will add to this table.
|
1. PERT |
(P + 4M + O )/ 6 Pessimistic, Most Likely, Optimistic |
|
2. Standard Deviation |
(P - O) / 6 |
|
3. Variance |
[(P - O)/6 ]squared |
|
4. Float or Slack |
LS-ES and LF-EF |
|
5. Cost Variance |
EV - AC |
|
6. Schedule Variance |
EV - PV |
|
7. Cost Perf. Index |
EV / AC |
|
8. Sched. Perf. Index |
EV / PV |
|
9. Est. At Completion (EAC) |
BAC / CPI, AC + ETC -- Initial Estimates are flawed AC + BAC - EV -- Future variance are Atypical AC + (BAC - EV) / CPI -- Future Variance would be typical |
|
10. Est. To Complete Percentage complete |
EAC - AC EV/ BAC |
|
11. Var. At Completion |
BAC - EAC |
|
12. To Complete Performance Index TCPI |
Values for the TCPI index of less then 1.0 is good because it indicates the efficiency to complete is less than planned. How efficient must the project team be to complete the remaining work with the remaining money? ( BAC - EV ) / ( BAC - AC ) |
|
13. Net Present Value |
Bigger is better (NPV) |
|
14. Present Value PV |
FV / (1 + r)^n |
|
15. Internal Rate of Return |
Bigger is better (IRR) |
|
16. Benefit Cost Ratio |
Bigger is better ((BCR or Benefit / Cost) revenue or payback VS. cost) Or PV or Revenue / PV of Cost |
|
17. Payback Period |
Less is better Net Investment / Avg. Annual cash flow. |
|
18. BCWS |
PV |
|
19. BCWP |
EV |
|
20. ACWP |
AC |
|
21. Order of Magnitude Estimate |
-25% - +75% (-50 to +100% PMBOK) |
|
22. Budget Estimate |
-10% - +25% |
|
23. Definitive Estimate |
-5% - +10% |
|
24. Comm. Channels |
N(N -1)/2 |
|
25. Expected Monetary Value |
Probability * Impact |
|
26. Point of Total Assumption (PTA) |
((Ceiling Price - Target Price)/buyer's Share Ratio) + Target Cost |
| Sigma σ |
|
| Return on Sales ( ROS ) |
Net Income Before Taxes (NEBT) / Total Sales OR Net Income After Taxes ( NEAT ) / Total Sales |
| Return on Assets( ROA ) |
NEBT / Total Assets OR NEAT / Total Assets |
| Return on Investment ( ROI ) |
NEBT / Total Investment OR NEAT / Total Investment |
| Working Capital |
Current Assets - Current Liabilities |
| Discounted Cash Flow |
Cash Flow X Discount Factor |
| Contract related formulas |
Savings = Target Cost – Actual Cost |


#14 Present Value formula is incorrect.
As written the formula only works for 1 year.
The proper formula should be:
PV= FV / ((1 + r)^term)
Correction made. Thanks a
Correction made. Thanks a lot for reporting the error
Sigma
For the sake of completeness, I guess it would be better to include the Six Sigma value too.
6 Sigma = 99.99985
Burn Rate formulae
The formulae for Burn Rate is
1/CPI where CPI = Cost performance Index.
PERT Formula Error
The formula you have listed for PERT is incorret. The actual formula is:
(P+(4xM)+O)/6
OR to make it less confusing for folks:
(Pessimistic Estimate + (4 x Most Likely Estimate) + Optimistic Estimate) / 6
PMBOK 4 Formula's
Hi Gurus,
May I know some one maintaining these formula's and updating for PMBOK4.
also I want to know How many Formula's are in Total in PMBOK4 and can someone please share if already got it.
Regards,
Can you pl. be more
Can you pl. be more specific how this question is related to PMP?
Thanks
Chandra
I looked all over google for
I looked all over google for it!! Thanks for the info..pfff! :)