Direct & Manage Project execution
Which option is NOT representative of the inputs, tools and techniques, and outputs of Direct and Manage Project Execution?
-
PMIS, Project Management Plan, and Deliverables
-
Deliverables, Approved Change Requests, and Project Management Methodology
-
Approved Change Requests, Recommended Defect Repair, and PMIS
-
Approved Corrective Actions, Project Management Methodology, and Implemented Preventive Actions
I find none of these options are correct, although the key seems to say C is correct.
Change requests are an output of D&M Project Execution and that change requests inculde recommended defect repair.
Anyone agree with me or do you see a reason why C is the right option?
sspawar
Wed, 12/19/2012 - 07:30
Permalink
Can tell the source of this q
Can tell the source of this q .
Prakash999
Wed, 12/19/2012 - 08:27
Permalink
Scordo Set10 / Q40
@sspawar it's Scordo Set10 / Q40.
i am more and more losing confidence on the correctness of answers given in scordo.
sspawar
Wed, 12/19/2012 - 11:14
Permalink
I am also unable to get it.
PMBOK specify clearly that
Defects repair are out put- and it is recommended Defects repair.
Something there is a wrong or someone who had solved these serieses, could tell about.