Cost baseline is usually represented using which curve or line?
Submitted by Anonymous (not verified) on Sat, 08/06/2011 - 03:16
Cost baseline is usually represented using which curve or line?
- Slanted line
- Z curve
- S-curve
- PQ curvec.
Answer : 'C' - S curve
The cost is low in the beginning and end, and high during the middle of the project.