ALL items included in the cost management plan
Submitted by Jp2786 on Tue, 05/27/2014 - 02:29
Which of the following are ALL items included in the cost management plan?
a) The level of accuracy needed for estimates, rules for measuring cost performance,
specifications for how duration estimates should be stated.
b) Specifications for how estimates should be stated , rules for measuring cost performance,The level of accuracy needed for estimates.
c) Rules for measuring team performance, The level of accuracy needed for estimates, Specifications for how estimates should be stated
d) Specifications for how estimates should be stated, The level of risks needed for estimates, Rules for measuring cost performance.
*****
Spoiler alert
Risk, Team performance and duration are not part of cost mgmt plan right so answer is B
Forums:
admin
Tue, 05/27/2014 - 03:58
Permalink
Yup, i will go with the
Yup, i will go with the Spoiler.
blissy1226
Fri, 11/20/2020 - 14:07
Permalink
This is a tricky question.
This is a tricky question. But in this case, I would go for the third choice. All of the answers are talking about cost estimates, except for the choice mentioned. - Paul Savramis