50% chance you will exceed
Submitted by Jp2786 on Tue, 05/27/2014 - 03:40
You just completed a cost estimate on the project, and you are assuming there is 50% chance you will exceed the estimate. You are:-
a) Below the mean
b) Above the mean
c) Above the median
d) Below the median.
How to go about this one?
Forums:
sunku65
Tue, 05/27/2014 - 13:55
Permalink
Assume your Cost estimate of
Assume your Cost estimate of the Project is $1,000,000 -/+ 10%.
That means the Range of the Project is $900,000 to 1,100,000.
Here mean is 100% i.e. $1,000,000. Below mean is $900,000 and above mean is 1,100,000.
Samething apply to your Question. 50% exceed means above mean.
Answer is b.
blissy1226
Fri, 11/20/2020 - 14:06
Permalink
Obviously, you are above
Obviously, you are above median. This gut feeling is telling that you need to revise whatever cost estimate that you have. - Paul Savramis