The following PMP® exam sample question is taken from the Free PMP Exam Simulator:

------------------------------

The total authorized budget for your IT project is $160,000 and Management Reserves are $20,000. You want to measure cost performance to see how the project is doing. In this context, the cost performance is against measured which of the following budget amounts?

A.) $180,000
B.) $160,000
C.) $20,000
D.) $140,000

------------------------------

Hint: The Cost Baseline includes all authorized budgets. The Cost Baseline is used to measure the Cost Performance of the project.

------------------------------

All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

Please click here for the correct answer and explanation.

Until next time,
Cornelius Fichtner, PMP
President, OSP International LLC - http://www.project-management-prepcast.com

B, p174, good Q