Doubts

--- An Organizational Breakdown Structure (OBS) shows

A. the functional units to which each member of the project team belongs.

B. which organizational units are responsible for which work packages.

C. the hierarchical management structure of the performing organization.

D. the reporting relationships which have been defined for the project.


--- Which process in integration management uses inputs from the largest number of other PMBoK processes?

A. Develop Project Management Plan.

B. Direct and Manage Project Execution.

C. Monitor and Control Project Work.

D. Perform Integrated Change Control.


--- A fixed-price contract represents

A. more risk for the buyer.

B. more risk for the seller.

C. a reasonable balance of risk for both buyer and seller.

D. an uncertain balance of risk for both buyer and seller.

admin's picture

What's your doubt ?

1 - B. which organizational units are responsible for which work packages.

2 - C. Monitor and Control Project Work.

3 - B. more risk for the seller.

had doubts because the answers mentioned are : B - A - D

Well, the answer to the question would be option D, but I have doubts like you. Hope you will get the right answer but don’t forget to share with us too. I suggest buying dissertations online which would be good.