The client demands changes to the product specification that will add only two weeks to the critical path. Which of the following is the best thing for the project manager to do? A. Compress the schedule 2 weeks. B. Cut scope to gain 2 weeks. C. Consult with project sponsor about options. D. Advise the client of the impact of the change.

The process for making changes are; 1. assess the impact, 2. identify option  3. get internal approval 4. consult and get buy in from customer. 

admin's picture

Not sure why answer would be C. Any explaination is given ?

I got this qts from i want to be PMP forum from linkedin

tricky...

Answer: C

A & B are invalid and can be eliminated completed because neither we can cut scope nor compress directly without analysing.

D - We cannot advice client of the change as we still did not finalize the path we are going to take i.e., Fast tracking or Crashing which now corners us to one answer C.

As a PM since this is a change to the product specification we need to consult project sponsor.