Early start calculation: Add 1 to early finish or not?

In some sources, early start equals early finish of the previous activity. In other sources, early start is early finish + 1 of previous activity. I know it is a technicality of how you do your project, but which way is correct in the PMP exam? I made mistakes between Rita and Headfirst practice questions because each uses a different method.

Thanks guys.

 

crushPMP's picture

 For PMP, do not add or sutract 1. Start with 0

 For understanding in full may refer blog post of 26 Dec 2012, at   er-sspawar.blogspot.in

ranatungawk's picture

Thanks for the information. It was also a doubt for me.... however it's explained clearly by following article

http://www.pmzilla.com/pmi-says-exam-start-0

Whatever material available for CPM in Rita is sufficient for exam. For better understanding you can watch

videos explaining CPM on You Tube. I recently cleared PMP and the logic given in Rita's worked for me.