To calculate EAC based on the cumulative COST & SCHEDULE performance...

Admin or PMP experts, please confirm if the
formula for calculating EAC based on the cumulative COST & SCHEDULE performance is:


PV + EV / [CPI x SPI]

Thanks,
PMPBOY

Wouldn't call myself a PMPExpert but EAC=AC+[(BAC-EV)/(CPIxSPI)]. I am not sure where you got the above formula from

 Well I dont understand from where u both got the formulae from, but If you could possibly provide the problem statement I can assure you I can definitely get you the solution in an elaborative step by step simplified way:)